The Deputy Director General for ITS, Igor Vladimirovich Lavrenov, shared an important event in the history of the plant: “On July 26, 2018, as part of the reconstruction and technical re-equipment of the production of injectable drugs on the basis of the Federal State Unitary Enterprise Moscow Endocrine Plant, Moscow, the work was carried out on lifting and installation in a design position of a complex of sublimation equipment on the 3rd and 4th floors of the Production building.
The total weight of the equipment complex is 29 tons, the weight of the heaviest unit is 15.5 tons. The total cost of the equipment is more than 148 million roubles.
A difficult lifting was made through technological openings in the outer walls with the simultaneous use of heavy specialized equipment in confined spaces.
The composition of the equipment complex:
- Sublimation unit SMART LYO SL 250-D
- Automatic loading/unloading system ALUS
- Refrigeration and vacuum unit
- SIP unit
The work was carried out with the involvement of the LLC Rustakelage M, specializing in complex rigging, under the supervision of specialists of the Enterprise and representatives of the manufacturer of technological equipment GEA Lyophil Gmbh".
The Enterprise expresses gratitude to all counterparties who participated in the complex technical operation of lifting and installation of equipment.
The deadline for construction and installation works and preparation of equipment with the capacity of 6 thousand units/hour and the performance of 18 thousand units/hour is scheduled for the 4th quarter of 2018.